PMP Exam Practice
Free reference

The PMP exam in 2026: content outline, domains, question types and scoring

PMI replaced the PMP exam on 9 July 2026. The current Examination Content Outline weights People at 33%, Process at 41% and Business Environment at 26%, across 26 tasks. This is that outline in plain English: what changed from 2021, how predictive and agile questions are mixed, and how to read, pace and think about a situational question.

The 2026 PMP exam at a glance

Every PMP exam scheduled on or after 9 July 2026 uses the new exam. It is built on the PMP Examination Content Outline (the ECO) dated July 2026, which PMI revised on 11 August 2026. The revised version is the one PMI links from its PMP pages today. The revision did not touch the domains, weightings or tasks: it removed a sentence about where the breaks fall and added the December 2026 training rule covered under eligibility below.

ItemCurrent position (checked 10 November 2026)
Content outlinePMP Examination Content Outline, July 2026, revised 11 August 2026
In force since9 July 2026, for every exam scheduled on or after that date
Domains and weightingsPeople 33%, Process 41%, Business Environment 26%
Tasks26: eight in People, ten in Process, eight in Business Environment
Questions180, of which 170 are scored and 10 are unscored pretest questions
Exam time240 minutes, with two 10-minute breaks
Approach mixAbout 40% predictive; the other 60% split between adaptive/agile and hybrid
Question typesMultiple choice (single and multiple response), case or scenario sets and graphic-based questions (both new), plus matching, enhanced matching, point and click and pull-down list
WherePearson VUE test centre (PMI's recommended option) or online with a proctor; paper-based only in mainland China
LanguagesEnglish plus 14 others
AttemptsUp to three within a one-year eligibility period
Keeping it60 professional development units (PDUs) every three years

Check the date on your study material. If a book, course or question bank talks about 42%, 50% and 8%, about 35 tasks or about 230 minutes, it was written for the January 2021 outline. PMI says the core principles have not changed, and that is true, but the weighting such material teaches is wrong for the exam you will actually sit.

What changed from the 2021 content outline

The 2021 outline served for five and a half years. The 2026 outline keeps the same three domains and the same 180-question length, and changes almost everything inside them.

AspectJanuary 2021 outlineJuly 2026 outline
People42%33%
Process50%41%
Business Environment8%26%
Tasks35 (14 People, 17 Process, 4 Business Environment)26 (8 People, 10 Process, 8 Business Environment)
Scored plus pretest175 plus 5170 plus 10
Exam time230 minutes240 minutes
Approach mixAbout half predictive, half agile or hybridAbout 40% predictive, 60% agile or hybrid
New question typesNoneCase or scenario sets; graphic-based questions
AI and sustainabilityNot namedBuilt into project scenarios rather than tested as topics of their own

Business Environment more than tripled, but much of it moved rather than appeared

The headline is Business Environment going from 8% to 26%. Read the task lists side by side and the picture is more nuanced. Risk, change control, issue management and governance were all Process tasks in 2021; in 2026 they sit in Business Environment, alongside compliance, continuous improvement, organisational change and the external environment. Removing impediments, a People task in 2021, has moved there too. So risk did not become less important when Process shrank. It changed address.

That matters for how you use older material. A 2021-era course still teaches you risk and change control perfectly well. What it under-teaches is the part that was genuinely small before: compliance, organisational change and reacting to a shifting external environment. Those three were most of an 8% domain before; now they are a real share of a 26% one.

People is now about alignment, not only the team

The 2021 People domain was heavy on internal team dynamics: building a team, emotional intelligence, virtual teams, ground rules, mentoring. In 2026, three of the eight People tasks are about stakeholders, one is about a shared vision, and communication and reporting have moved in from Process. Team leadership and conflict are still there. Emotional intelligence and virtual teams are no longer task names; in my reading the behaviour is still examined, just through leadership and conflict scenarios rather than as topics of their own.

The exam looks more like work

The two new question types, case or scenario sets and graphic-based questions, put dashboards, charts and project artefacts in front of you. PMI's own account of the change is that AI and sustainability now appear as part of the context a candidate has to navigate: an AI-generated dashboard in a scenario, a sustainability constraint inside a quality, compliance or risk decision. You are not asked what AI is. You are asked what a project manager does when it is in the room.

PMI's position is that the new exam is not more difficult, just more relevant, and that the scoring method has not changed. My view, having spent most of a career on the delivery side of large programmes, is that the new weighting is a more honest picture of where projects actually fail: rarely in the Gantt chart, often in governance, compliance and the organisation around the project.

The three domains and 26 tasks, in plain English

The task names below are PMI's. The descriptions are mine, written from the enablers PMI lists under each task. PMI is explicit that the enablers are illustrative examples rather than an exhaustive list, and that every exam includes questions on every task in a domain. So none of the 26 can safely be skipped.

Domain I: People (33%)

TaskNameWhat it tests in practice
1Develop a common visionGetting key stakeholders to one picture of the outcome, keeping it current, and working out why people have drifted from it when they have.
2Manage conflictsFinding the source and context of a conflict, agreeing a resolution approach, and keeping the team's ground rules alive rather than laminated.
3Lead the project teamSetting expectations, empowering people, choosing a leadership style that fits, clarifying roles, and representing the team outwards.
4Engage stakeholdersIdentifying and analysing stakeholders, tailoring communication to them, running the engagement plan, and building the trust needed to influence.
5Align stakeholder expectationsCategorising stakeholders, surfacing what each expects, and facilitating the conversation when those expectations collide.
6Manage stakeholder expectationsInternal and external customer expectations: aligning outcomes to them and watching satisfaction over the life of the project.
7Help ensure knowledge transferDeciding which knowledge is critical, capturing it, and creating conditions in which people actually share it.
8Plan and manage communicationA communication strategy, transparency, feedback loops, and reporting that serves sponsors and the governance process.

Domain II: Process (41%)

TaskNameWhat it tests in practice
1Develop an integrated project management plan and plan deliveryAssessing size and complexity, recommending a predictive, agile or hybrid approach, then building, maintaining and deciding from an integrated plan.
2Develop and manage project scopeDefining and decomposing scope and getting stakeholders to agree to it.
3Help ensure value-based deliveryAgreeing what value means with stakeholders, prioritising by it, delivering incrementally where that helps, and tracking benefits.
4Plan and manage resourcesPlanning resources from requirements and balancing what is needed against what is available.
5Plan and manage procurementProcurement planning, contract types, negotiation strategy, supplier management and checking that the agreement delivers its objectives.
6Plan and manage financeFinancial needs, contingency for risk, spend tracking and reporting, managing reserves, and handling variance through governance.
7Plan and optimize quality of products/deliverablesQuality requirements, processes and tools, regulatory compliance, cost of quality and sustainability, reviews and continuous improvement.
8Plan and manage scheduleScheduling to fit the chosen approach, estimating (milestones, dependencies, story points), baselining, and analysing variance.
9Evaluate project statusMetrics, the artefacts the project needs and their accessibility, assessing progress, and communicating status.
10Manage project closureClosure criteria, stakeholder acceptance, readiness for transition to operations or the next phase, and the closing work itself.

Domain III: Business Environment (26%)

TaskNameWhat it tests in practice
1Define and establish project governanceStructure, rules, reporting, ethics and policy drawn from organisational process assets, plus success metrics and escalation paths with thresholds.
2Plan and manage project complianceSecurity, health and safety, sustainability and regulatory requirements: classifying them, spotting threats, and measuring whether the project complies.
3Manage and control changesRunning change control, reporting the status of proposed changes, implementing approved ones and keeping documentation current.
4Remove impediments and manage issuesAssessing and prioritising blockers, choosing an intervention, and recognising the moment a risk has become an issue.
5Plan and manage riskRisk planning, identification and analysis, the register, responses (including security and sustainability risks), and communicating risk status.
6Continuous improvementUsing lessons learned and keeping improvement processes and organisational process assets up to date.
7Support organizational changeAssessing culture and the effect of organisational change on the project, and deciding what that requires.
8Evaluate external business environment changesWatching regulation, technology, geopolitics and markets, and reprioritising scope or backlog when they move.

A useful way to hold the three domains in your head: People is how you lead and align humans, Process is the planning and control spine of delivery, and Business Environment is what you do when the rules around the project move. A surprising number of exam questions are decided by spotting which of the three the stem is really about.

PMP question types in 2026

The exam has 180 questions. Ten are pretest questions that PMI is trialling for future exams; they do not count, they are placed at random, and you cannot tell which they are. The other 170 decide your result.

TypeWhat you doDelivery modes (PMI's labelling)
Case or scenario (new)Read a longer description of a business, a project or a decision, sometimes with charts, then answer a series of questions on itAll
Graphic-based (new)Interpret a chart, graph, diagram or image and answer from itAll
Multiple choice, single responseChoose the one correct optionAll
Multiple responseChoose every correct option from a list with more than oneAll
MatchingDrag items from one column to pair them with items in anotherComputer at a test centre only
Enhanced matchingMatching onto a chart or diagram, usually by drag and dropComputer at a test centre only
Point and clickClick the correct area of an image that has hidden hotspotsComputer at a test centre only
Pull-down listPick the answer from a drop-down listComputer at a test centre only

PMI marks four of the types as available only on computer-based testing at a test centre, so the mix you meet depends on how you sit the exam. PMI does not publish how many questions of each type appear, and says the number per type and per approach varies by exam form. Prepare for all of them either way.

What the graphic and case items are likely to show you

PMI describes the new items as built around dashboards, project artefacts, tools and data. PMI does not list the charts, so this list is mine: be fluent with a burndown and burnup chart, a cumulative flow diagram, a Gantt chart with a critical path, an earned-value curve, a risk heat map, a RACI matrix and a stakeholder power-interest grid. The skill being tested is reading what the picture says about the project, not drawing it.

Practicalities on the day

  • Breaks lock sections. There are two 10-minute breaks. Once you start a break you cannot return to the questions before it, so review your flagged questions before you take it.
  • Calculator. One is built into the computer-based exam, and at a test centre you can ask for a handheld one.
  • Notes. Test centres provide scratch paper or erasable boards; you do not choose which.
  • Tutorial and survey. Both are optional and sit outside the 240 minutes.
  • Online. Online proctored exams need a system test and a longer check-in, and you may be asked to show your ID again after a break.

Predictive, agile and hybrid in the exam

PMI states that about 40% of the questions represent predictive approaches and the remaining 60% are divided between adaptive/agile and hybrid. In 2021 the split was about half and half. The approaches are spread across all three domains rather than confined to one, so a People question can be set on a Scrum team and a Business Environment question on a stage-gated construction project.

The approach is itself examinable. Process task 1 includes assessing a project's complexity and recommending a predictive, agile or hybrid approach, so some questions turn on whether the project should be run differently, not on how to run it as it is.

Recognising which world a question is in

Most stems do not say "this is an agile project". They tell you through vocabulary, and the right answer usually respects the conventions of that world.

Cue in the stemProbablyWhat a good answer tends to respect
Baseline, approved project management plan, change control board, WBS, phase gate, sponsor sign-offPredictiveThe plan as the agreement; formal change control; the authority of the sponsor or the change control board over the baseline
Product owner, backlog, sprint or iteration, velocity, retrospective, definition of doneAgileA self-organising team; the product owner's ownership of priority; change absorbed through backlog refinement; the project manager as servant leader
Iterative delivery inside fixed governance gates, a fixed-price supplier feeding an agile team, a regulatory milestone with incremental build behind itHybridBoth layers at once: honour the governance commitment and the way the delivery team works, without forcing one onto the other

The classic traps

  • Predictive reflexes on an agile team. Raising a formal change request because the product owner reprioritised the backlog, or assigning tasks to a team that is supposed to pull its own work.
  • Agile reflexes on a predictive project. Quietly absorbing a scope change to keep a stakeholder happy when there is a baseline and a change control process.
  • Treating hybrid as "pick one". In a hybrid scenario the wrong answers usually ignore one of the two layers: they either bypass the governance gate or micro-manage the iterative team.

My view from enterprise delivery: hybrid is where most real projects live. An ERP programme with a fixed go-live, a regulator and a vendor contract on one side and iterative configuration sprints on the other is not an edge case, it is Tuesday. The 60% figure reflects that, and it is why hybrid questions reward judgement more than vocabulary.

How to read a situational question

Most PMP questions describe a situation and ask what the project manager should do. Every option is something a reasonable person might do, and often more than one is correct in the abstract. You are choosing the best one, and frequently the best first step. That is a different skill from knowing the material, and it is the one that decides the exam.

A method that works

  1. Read the last sentence first. "What should the project manager do first?", "next?", "best?" and "what should have been done?" are four different questions. "First" is about sequence, and the answer is usually to understand before acting. "Should have" asks what would have prevented the situation.
  2. Place the scenario. Which approach is it, where in the life cycle are we, and who holds the authority here: you, the sponsor, the product owner, a change control board, a functional manager?
  3. Strip the noise. Names, history and emotion are decoration. Find the actual problem: a conflict, a proposed change, a risk that has occurred, a misunderstanding, a compliance threat, a blocker.
  4. Eliminate the usual distractors. Acting before understanding (implement it now, reject it now); escalating something within your own authority; bypassing the agreed process; and doing nothing useful (document it and carry on).
  5. Choose between the last two. Prefer the option that deals with the root cause, involves the right people directly, stays within the project manager's authority and protects the value the project exists to deliver.

PMI's own samples point the same way. PMI publishes three sample questions on its PMP page. In all three, the correct answer is to assess the situation and work through it with the right people: evaluate a stakeholder's change through change control, meet a stakeholder who is undermining the plan and review roles and authority, assess a supplier delay and evaluate options with the team. The wrong answers include rejecting a change outright, implementing it to please the customer, compressing the schedule immediately, telling the sponsor all is well and escalating for direction before anyone has looked.

A worked example

This one is mine, written to the 2026 outline. A hybrid programme has a fixed regulatory release date; the internal team works in two-week iterations. Mid-iteration, the compliance officer tells you a new data-retention rule applies from next quarter and that one feature in the backlog may breach it. The product owner wants to keep the feature in the next release because a key customer asked for it. What should the project manager do first?

  • A. Remove the feature from the backlog to protect compliance.
  • B. Let the team finish the iteration and raise it at the retrospective.
  • C. Work with the compliance officer and the product owner to assess the rule's impact on the feature and its priority.
  • D. Escalate to the sponsor, since compliance overrides the product owner.

The answer is C. A acts before anyone knows whether there is a breach and overrides the product owner's authority over the backlog. B parks a compliance threat in a meeting that exists to improve the team's way of working. D escalates before the size of the problem is known. C is assess-first, collaborative and uses the people who own each half of the decision; it touches compliance (Business Environment task 2), the external environment (task 8) and stakeholder alignment (People task 5) at once, which is typical of the 2026 exam. Notice that if the next question says the assessment confirmed a breach, the best answer changes, probably to taking the feature through change control or reprioritising it with the product owner. Sequence is the point.

Case sets and graphic items

  • Case sets: skim the case once for its shape (who, what approach, what is going wrong), then read each question and go back for the specific detail it needs. Do not try to memorise the case before you know what is being asked.
  • Graphic items: read the title, the axes, the units and the legend before you read the question. Most wrong answers on charts come from misreading what is being measured, not from misjudging the project.

How the PMP is scored, and what that means in practice

What PMI says

  • It is criteria-based. The handbook describes PMI's exams as determining pass or fail by whether you meet the criteria for a qualified person in the role, which for the PMP is an experienced project manager. The passing score is set by psychometric analysis.
  • Only scored items count. You are evaluated on the 170 scored questions. The 10 pretest questions do not affect your result.
  • The report gives pass or fail, plus diagnostics. Alongside the overall result you get diagnostic information on your performance in each domain, for passing and failing candidates alike.
  • The result on screen is preliminary. For the PMP, a result shown at the end of a computer-based session is preliminary until PMI confirms it. The official report is available online no later than 10 business days after the exam; paper-based candidates receive theirs by email within 6 to 8 weeks.
  • Nothing changed in 2026. PMI states that the scoring method was not changed by the new exam.

What that means when you sit it

  • There is no published pass mark. PMI does not publish a percentage, so any precise figure you see on a forum is a guess. With a criteria-based standard it is also the wrong target. Aim to be clearly competent in every domain; the per-domain diagnostics exist because a weak domain shows.
  • Treat every question as scored. You cannot identify the pretest items, and a question that feels unfamiliar is far more likely to be a scored one you have not prepared for than a trial item.
  • Assume no partial credit. PMI does not publish how multiple-response or matching items are marked. Do not rely on getting half of a multiple-response item right; get all of it right.
  • Answer everything. An unanswered question cannot be marked correct. Flag the doubtful ones, give your best answer anyway, and return to them before the next break locks the section.
  • Pace it. 240 minutes for 180 questions is 80 seconds a question. The outline describes the 240 minutes as time to respond; PMI's new-exam FAQ describes 240 minutes including the two breaks. Plan on about 75 seconds a question and you are safe under either reading. Case sets take longer to read, so bank time on the short single-response items.

The practical consequence of all this is the one PMI makes in its outline: the exam assesses whether you can apply practice to situations, not whether you can recite it. Spend your preparation where that is tested.

PMP eligibility in brief

You apply first and sit the exam once PMI approves the application. The 2026 outline widened the education side, mapping the education levels to European (EQF) and international (ISCED) qualification levels so that vocational and non-traditional routes are recognised more clearly.

EducationExperience leading projects (non-overlapping, within the last 10 years)
Secondary school completion (high school diploma or equivalent)60 months (5 years)
Associate-level degree, higher certificate, or advanced technical or vocational programme48 months (4 years)
Bachelor's degree or higher, or a qualification officially mapped to bachelor level36 months (3 years)
Bachelor's or postgraduate degree from a programme accredited by PMI's Global Accreditation Center (GAC)24 months (2 years)

Experience

The experience has to be in leading and directing projects, in a professional setting. It does not have to be paid. School projects, academic research for a degree, planning personal events and home improvement do not count, and PMI asks you to leave routine operational or administrative work out of your project descriptions. Experience is counted in months, so two overlapping projects count once for the months they overlap.

Training

  • You need 35 hours of project management training aligned to the content outline, recorded in your application and subject to audit.
  • From 1 December 2026, live instructor-led training (in person or online) counts only when delivered by a PMI Authorized Training Partner, a China Registered Education Provider, or an eligible accredited academic programme, including GAC programmes. Self-paced, on-demand courses can still come from any organisation. Training completed before 1 December 2026 remains eligible under the current rules.
  • An active CAPM certification covers the 35 hours. You still have to meet the education and experience requirements.

Practice questions are not training hours. PMI says plainly that books and practice exams alone are not accepted as eligible training. That includes practice apps, this one too. Use them to prepare; get your 35 hours from a qualifying course.

Audit, eligibility period and retakes

  • A percentage of applications are selected at random for audit. If yours is, you have 90 days to provide the documentation, and your eligibility period starts once the audit is passed.
  • Once approved, you have one year to pass and up to three attempts in that year; the second and third attempts carry fees.
  • After three unsuccessful attempts you wait a year from the last one before reapplying. If the year runs out before you pass, you reapply, without a waiting period.

Preparing for the 2026 PMP: what I would do

This is opinion, from someone who has spent years running delivery and architecture functions rather than teaching exam courses. It is how I would spend the hours.

  • Start with the outline itself. It is short. Read every task and its enablers. They are illustrative, but they tell you the flavour of what each task means to the people who write the questions.
  • Split your time by weight, then bias towards weakness. Business Environment deserves about a quarter of your hours. Most material written before July 2026 gives it far less, because it was worth 8%.
  • Do not treat the PMBOK Guide as the syllabus. PMI itself says there are noticeable differences between the outline and the PMBOK Guide, and that the exam is not written from any single text. The PMBOK Guide and the Agile Practice Guide are among the references PMI's question writers cite most, which makes them useful background, not a checklist.
  • Practise situational questions in volume, and study the wrong answers. The value of a practice question is in the explanation of why the second-best option loses. After a few hundred, the patterns described above become reflexes.
  • Sit at least one full-length, timed mock. Four hours of judgement calls is an endurance event. Find out where your attention goes before exam day, not during it.
  • Learn the agile and hybrid vocabulary properly. With 60% of questions set in agile or hybrid contexts, not knowing what a product owner may and may not decide costs points across all three domains.
  • Get comfortable with charts. Finance and schedule tasks still ask you to analyse variance and size contingency, and graphic-based items put the data in front of you. Being able to read a burndown or an earned-value curve at a glance is worth more than memorising a long list of formulas.

If you are mid-way through older material, or already certified

PMI's advice to people studying older material is to keep going, because the core principles have not changed. I agree, with two additions: top up on compliance, organisational change and the external environment, and practise the new case and graphic-based formats. Legacy PMI e-learning bought before the change stays available in the myPMI learning platform until 31 December 2026.

If you already hold the PMP, none of this affects you. Your certification remains valid, and you maintain it as before with 60 PDUs in each three-year cycle.

Practise it, not just read it

Reading the outline tells you what is tested. Passing depends on making the call, under time pressure, again and again. PMP Exam Practice gives you situational questions across People, Process and Business Environment, with an explanation behind every answer that says why the best answer beats the merely correct one. Weakest-topic surfacing shows your best score and pace per topic, so revision goes where it is needed.

The free tier gives you a daily practice allowance with explanations on every answer. Pro adds unlimited practice, timed mock exams on the exam clock, and an AI tutor that runs on your iPhone through Apple Intelligence, so your questions never leave the device.

Use it in your browser Tell me when the iPhone app lands No install · free account · Preparing for submission on iPhone

Common questions

When did the new PMP exam start?

PMI launched the updated exam on 9 July 2026. Every PMP exam scheduled on or after that date uses the new content outline, dated July 2026 and revised by PMI on 11 August 2026.

What are the PMP domain weightings in 2026?

People 33%, Process 41% and Business Environment 26%, across 26 tasks. The January 2021 outline it replaced was 42%, 50% and 8% across 35 tasks.

How many questions are on the PMP exam, and how long is it?

180 questions, of which 10 are unscored pretest questions, in 240 minutes with two 10-minute breaks. The optional tutorial and survey are not counted in the 240 minutes.

What is the passing score for the PMP exam?

PMI does not publish one. The exam is criteria-based: the passing standard is set by psychometric analysis against what an experienced project manager should be able to do, and the score report gives pass or fail plus diagnostic feedback for each domain.

Is the 2026 PMP exam harder than the old one?

PMI says it is not more difficult, just more relevant, and that the scoring method has not changed. What changed is where the questions come from: Business Environment rose from 8% to 26%, about 60% of questions are set in agile or hybrid contexts, and there are new case and graphic-based question types.

Do I need to retake the PMP if I already hold it?

No. An existing PMP stays valid and is maintained exactly as before, with 60 professional development units in each three-year cycle.

About the author

Magnus Oxenwaldt is VP Group AI at Columbus Global. Two decades in enterprise architecture — ERP, integration, customer engagement, and now AI. He hosts the Future Bytes podcast, speaks at executive forums and board off-sites, and writes at oxenwaldt.com.